Dubai, Spain, Türkiye and Cyprus secure off-plan payments differently

David Le David Le
Person in a white hard hat and a green high-visibility vest, seen from behind, looking down at a blank sheet on a clipboard, with a building under construction and scaffolding behind; face not clearly visible, no readable text

Dubai requires a project escrow account, Spain a guarantee and a separate account, Türkiye one of four safeguards at 30 homes or more, and Cyprus gives a buyer who deposits the contract a charge on the land.

A buyer paying for a home still under construction depends on local law for where the money sits and who repays it if the developer fails. In all four places, the protection attaches to a formality: a register entry, a guarantee document, a designated account or a deposit at the land registry.

What the law provides

Place What the law provides How the money is released If the developer fails
Dubai A project escrow account at an agent accredited by the Land Department (DLD) for off-plan payments, dedicated to construction and shielded from the developer’s creditors; a sale not entered in the Interim Property Register is void Per the agreement with the agent, whose engineer checks the stages, says the DLD; 5% is held back until 1 year after units are registered to buyers On cancellation by the Real Estate Regulatory Agency (RERA), refund requested from the agent within 14 days, or from the developer for payments made outside the account; the developer repays any shortfall within 60 days, which RERA may extend
Spain From the building licence, an insurance policy or bank guarantee for all sums advanced, with taxes and legal interest, and a special bank account for them Additional provision 1 sets no schedule; the account may be used only for building costs If building does not start or end on time, rescission with refund and legal interest, claimed from the insurer or bank if a formal demand on the developer goes unmet for 30 days
Türkiye From 30 homes, before sales start: building completion insurance, or a bank guarantee letter, a progress-payment account or a linked loan Under the progress-payment option, payments sit in a blocked account in the seller’s name and leave it only against progress Insurance: the buyer’s bank payments, linked-loan amounts excluded, plus legal interest, principal capped at the guarantee note, if the seller goes bankrupt or misses the delivery deadline by 12 months, subject to exclusions; a bank guarantee letter is payable on first demand
Cyprus The Law sets no escrow, guarantee or insurance; a contract deposited at the District Lands Office within 6 months of signing creates a charge on the property Not regulated by the Law The charge secures the sum paid and acts as a mortgage for damages awarded instead of transfer to a buyer who performed

Dubai fixes the account by statute and the release by agreement

Law No. (8) of 2007 leaves the account’s terms to a written agreement between developer and escrow agent (Article 7).

The 2010 bylaw makes a developer’s bankruptcy a ground for RERA to cancel a project (Article 23). Law No. (19) of 2020 makes the developer refund all purchasers’ payments, under the procedures of Law No. (8) of 2007, once RERA has cancelled a project by final reasoned decision, and a special tribunal liquidates the project, except in the Dubai International Financial Centre.

A buyer who wants the money back from a project that RERA has not cancelled must go to court, the DLD says. The DLD also says RERA may excuse a developer from opening an escrow account.

Spain makes an insurer or a bank the payer

Additional provision 1 of Law 38/1999, in the version in force since 1 January 2016, covers housing promoters who take advances during construction. From the grant of the building licence they must guarantee repayment by a surety insurance policy or a joint-and-several bank guarantee, and collect advances through a special bank account used only for construction.

The insurer cannot refuse to pay because the developer left the premium unpaid. A bank guarantee lapses two years after the developer’s breach unless the buyer has by then demanded rescission and repayment.

The weekly bulletin

Leave your email address. We will keep you informed on citizenship by investment, international capital flows and global mobility.

Türkiye ties the safeguard to the size of the project

Law 6502 requires registration at the land registry or a notarised promise to sell (Article 41), and forbids the seller to ask for any payment before a valid contract exists.

The Regulation on Prepaid Housing Sales requires the safeguard for projects of 30 homes or more and accepts another method the Ministry approves as covering all payments (Article 12). Under the progress-payment option, the bank returns the unreleased balance if the seller fails to deliver (Article 15).

Building completion insurance runs on general conditions that the Insurance and Private Pension Regulation and Supervision Agency publishes, in force since 13 June 2024.

For a prepaid sale under Law 6502, the insurer covers the seller’s bankruptcy and a failure to deliver within 12 months after the delivery deadline, unless the cause is one the conditions leave out of the cover, among them natural disasters, war and the buyer’s own withdrawal (Articles 7 to 9).

Each buyer whose papers the seller sends on gets a guarantee note covering only payments made through a bank: cash, cheques, promissory notes and linked-loan amounts are left out. The insurer sets a maximum cover limit for the part of the project sold off-plan (Articles 7 and 9, Annex 1).

Payouts and guarantees under the insurance cannot enter a bankruptcy or liquidation estate or be attached (Law 6502, Article 42).

The insurer may pay or have the building finished. A cash payment falls due 45 days after notice at the latest; the period stops while documents are missing or the review is delayed through no fault of the insurer (Article 20).

Cyprus relies on a charge on the land

Under the Sale of Immovable Property (Specific Performance) Law, either party may deposit the written contract within 6 months of signing if a seller is registered as owner of the property or the parcel containing it; the charge ranks from the day of deposit (sections 3 and 5).

The charge secures the sum the buyer has paid until the court orders transfer or damages are paid (section 5(3)). On a winding-up or bankruptcy order against the seller, the Companies Law and the Bankruptcy Law apply (section 5(11), added by a 2023 amendment); that provision does not say what becomes of the charge.

What a payment from Vietnam has to reach

  • Dubai: the project’s escrow account, whose number and completion percentage the DLD’s Dubai REST app shows, and an entry in the Interim Property Register, within 90 days of signing under the DLD’s service terms.
  • Spain: the bank account named in the contract and the guarantee document delivered at signing. The insurer owes only the sums the buyer can show were paid.
  • Türkiye: a contract in registered or notarised form, the safeguard named in it from 30 homes, and payment through a bank.
  • Cyprus: a deposit of the contract at the District Lands Office within 6 months. Without the deposit there is no charge, though a court may still order a written contract performed (section 6(2)).

How money may leave Vietnam for a purchase abroad is covered in an earlier piece.

What this article has not established

Thailand is not covered: the Department of Lands address for the English text of the Condominium Act returned “not found” in a browser on 5 November 2026. Neither are Abu Dhabi and the other emirates.

The Dubai texts are English translations that say the Arabic prevails. No law amending Law No. (8) of 2007 turned up there or in web searches.

The DLD’s project-registration page lists a 30% guarantee (completion of 30% of construction, a bank guarantee or a cash deposit) as a condition of registering a project. A word search of eight Dubai instruments and the DLD’s compilation of Dubai real estate laws found “guarantee” only in a mission statement, and the page does not say who can call on it.

Law No. (8) of 2007 does not say whether a reservation fee paid before the contract counts as a payment into the account.

The Spanish and Cypriot texts were read in consolidated versions that carry no legal value, the Turkish general conditions as page images of a scanned PDF. No policy’s own special conditions were read.

Insolvency statutes were searched, not read through: a word search found no escrow or off-plan sales in the English translation of the UAE federal bankruptcy law (Decree-Law No. (51) of 2023), no advances on homes in Spain’s Ley Concursal and no prepaid housing sales in Türkiye’s Enforcement and Bankruptcy Law. Cyprus’s insolvency laws were not read. No developer, project or register was checked.

The Legation Times writes its content from published documents; nothing here is legal, tax or investment advice. Spotted an error? Send a correction request; for content rights, send a takedown request.